FIDIC claim tayyorgarligi cheklisti
FIDIC shartnomalari bo‘yicha claim topshirishdan oldingi 12 tekshiruv punkti.
-
Notice o‘z vaqtida
Notice shartnomaviy muddatda, odatda voqea ma’lum bo‘lgan kundan 28 kun ichida yuborilgan.
-
Notice formasi
Rasmiy tartib bajarilgan: to‘g‘ri adresat, yozma shakl va tegishli clausega havola.
-
Alohida event file
Voqea bo‘yicha alohida fayl ochilgan: chronology, letters, instructions, RFI, meeting minutes va photos.
-
Contemporary records
Yozuvlar voqea davomida kunlik yoki haftalik yuritilgan, keyin qayta tiklanmagan.
-
Causation
Zanjir ko‘rsatilgan: event → consequence → delay va/yoki cost.
-
Oqibatlarni ajratish
Delay, disruption va prolongation costs bitta summaga qo‘shilmay, alohida ko‘rsatilgan.
-
Contractual entitlement
Claim huquqini beruvchi contract clauses va Particular Conditions aniqlangan.
-
Relief turi
Talab aniq: EOT, additional payment yoki ikkalasi.
-
Delay analysis
EOT uchun programme impact va critical path logic tahlil qilingan.
-
Cost evidence
Summalar invoices, timesheets, calculations va quotations bilan tasdiqlangan.
-
Oraliq muddatlar
Fully detailed claim va keyingi submissions muddatlari tekshirilgan.
-
Amaldagi versiya
Contract va appendices amaldagi versiyasi tekshirilgan; matn loyiha uchun moslashtirilgan.