The FIDIC Rainbow Suite: how to choose the right book
Red, Yellow, Silver, Pink and the rest of the FIDIC books — how they differ, who carries design risk, and which form to choose for your project.
Practical article map
Start with the contract issue, test the evidence, then define the practical next step.
FIDIC is not a single contract but a whole family of standard conditions, commonly called the “Rainbow Suite”. Each book is colour-coded and designed for a particular project type and a particular allocation of risk. A mistake at the selection stage is expensive: it runs through the entire life cycle of the contract — from pricing to dispute resolution.
Let’s unpack the logic of the suite so the choice becomes obvious.
The key question: who designs?
Risk allocation in FIDIC starts with the answer to one question — who is responsible for the design.
- If the Employer designs and the Contractor builds “to the drawings” — that’s the Red Book.
- If the Contractor designs — that’s the Yellow Book (or the Silver Book, if even more certainty is needed for an investor).
Almost everything else follows: the payment mechanism, the role of the Engineer, and who is liable for errors in the design documents.
The three core books
Red Book — Construction
The classic form for Employer-designed works. Payment is by re-measurement based on a Bill of Quantities (BoQ). An independent Engineer administers the contract. Design-error risk stays with the Employer. Suited to roads, bridges and civil works.
Yellow Book — Plant & Design-Build
The Contractor designs and builds. The price is a lump sum. The Contractor is responsible for the design’s fitness for purpose. Used for electro-mechanical works and contractor-designed facilities.
Silver Book — EPC / Turnkey
A turnkey form for project-financed schemes (BOT, IPP). There is no independent Engineer — there is an Employer’s Representative. The Contractor takes on almost all risk, including most of the “unforeseeable”, in exchange for a risk premium. The investor gets maximum price and time certainty.
Rule of thumb: the more price and time certainty the Employer needs, the more risk sits with the Contractor — and the higher the price.
The special books
- Pink Book (MDB Harmonised) — a version of the Red Book harmonised with the development banks. This is the key form for Uzbekistan: World Bank, ADB and EBRD projects use it.
- Green Book — a short form for small and simple works.
- Gold Book (DBO) — design-build-operate, with a long (usually 20-year) operation period.
- Emerald Book — underground works; introduces a Geotechnical Baseline Report for a fair allocation of geo-risk.
- White Book — a consultant services agreement (not a construction contract).
How to choose: a short checklist
- Who designs? Employer → Red. Contractor → Yellow/Silver.
- Need maximum price/time certainty? Yes → Silver.
- Financed by a development bank? Yes → Pink Book + the bank’s Particular Conditions.
- Are the works small and simple? → Green Book.
- Need long-term operation? → Gold Book (DBO).
Choosing the book is a strategic decision about risk allocation, not a formality. If you are unsure which form suits your project, start with the interactive rainbow suite or request a consultation.
Bridge Consult
Prepared by the experts at Bridge Consult — a practising team in FIDIC contracts, claims and MDB projects. Need help with a real contract?
Request a consultation