Terms Library
FIDIC Glossary
Key FIDIC contract terms — in English, as in the documents, with plain-language definitions.
Bill of Quantities (BoQ)
Bill of Quantities
A priced schedule of work quantities; the basis of payment in the Red/Pink Book (re-measurement).
Claim
Claim
One party’s request to the other for additional payment, time or another entitlement. In 2017, a single procedure for both parties (Clause 20).
Contractor
Contractor
The party carrying out the works; in Yellow/Silver also responsible for the design.
DAAB
Dispute Avoidance/Adjudication Board
Dispute Avoidance/Adjudication Board — a standing body to avoid and resolve disputes; its decisions are binding with immediate effect.
Defects Notification Period (DNP)
Defects Notification Period
The period after taking-over during which the Contractor must remedy notified defects (Clause 11).
Delay Damages
Delay Damages
Pre-assessed damages for delayed completion (liquidated damages), usually capped.
Determination
Determination
The Engineer’s decision to agree or determine a matter where the parties have not agreed (Sub-Clause 3.7).
Employer
Employer
The party commissioning the works and carrying the payment obligations; in the Silver Book it acts through the Employer’s Representative.
Employer's Representative
Employer’s Representative
Manages the contract in the Silver Book instead of an independent Engineer; acts in the Employer’s interest.
Engineer
Engineer
A person appointed by the Employer to administer the contract (Red/Yellow). Must act neutrally when making determinations (Sub-Clause 3.7).
Exceptional Event
Exceptional Event
An event beyond the parties’ control (Force Majeure in 1999), giving relief from liability (Clause 18).
Extension of Time (EOT)
Extension of Time
The Contractor’s entitlement to extend the completion time for delays it is not responsible for (Sub-Clause 8.5).
Final Statement
Final Statement
The Contractor’s statement at completion to finally determine the amounts due (Clause 14).
Interim Payment Certificate (IPC)
Interim Payment Certificate
The Engineer’s certificate for an interim payment for completed work and delivered materials (Clause 14).
Notice of Dissatisfaction (NOD)
Notice of Dissatisfaction
A formal notice of disagreement with a DAAB decision, opening the way to arbitration. Missing the deadline makes the decision final.
Performance Certificate
Performance Certificate
Issued after defects are remedied and the DNP ends; signifies that the Contractor’s obligations are fulfilled.
Performance Security
Performance Security
A bank guarantee/security provided by the Contractor as a performance guarantee (Sub-Clause 4.2).
Pink Book / MDB
MDB Harmonised form
A Red Book version harmonised with the development banks (World Bank, ADB, EBRD) for projects they finance.
Programme
Programme
The detailed execution schedule submitted by the Contractor; the basis for time control (Sub-Clause 8.3).
Provisional Sum
Provisional Sum
A sum included in the price for work/supply to be defined later; spent on the Engineer’s instruction.
Taking-Over Certificate
Taking-Over Certificate
Confirms the Works are complete and taken over by the Employer; starts the Defects Notification Period (Clause 10).
Tests after Completion
Tests after Completion
Operational tests after taking-over (Yellow/Silver, Clause 12) confirming design performance.
Tests on Completion
Tests on Completion
Tests before taking-over confirming the Works meet the requirements (Clause 9).
Time-bar (28 days)
28-day time-bar
The deadline to give a notice of claim. Missing it can forfeit the party’s right to the claim (Sub-Clause 20.2.1).
Unforeseeable Conditions
Unforeseeable Conditions
Physical site conditions an experienced Contractor could not foresee (Sub-Clause 4.12); risk allocation depends on the book.
Variation
Variation
A change to the Works initiated by the Engineer/Employer under Clause 13; valued, and may adjust price and time.