FIDIC 1999 vs 2017: what changed
From 20 clauses to 21, from the DAB to the DAAB, a single claims procedure and a focus on avoiding disputes. The main differences between the first and second editions of the rainbow suite.
In 2017 FIDIC released the second editions of the Red, Yellow and Silver Books. This is not a cosmetic tweak but a serious overhaul: the contracts became more detailed, more procedural and far more oriented towards avoiding disputes. Let’s go through the key differences.
Structure: 20 → 21 clauses
The 1999 editions had 20 clauses, with claims and disputes living in Clause 20. The 2017 editions have 21 clauses, and the material is redistributed:
- Clause 20 — now the single claims procedure for both parties.
- Clause 21 — a separate clause on disputes and arbitration (the DAAB).
A single claims procedure
Previously, the Contractor’s and Employer’s claims were handled differently. The 2017 editions introduced a symmetrical mechanism: the same notice-and-substantiation procedure applies to both parties. The preclusive notice period — 28 days — was retained.
From the DAB to the DAAB
The dispute board shifted its emphasis from resolution to avoidance: the Dispute Adjudication Board (DAB) became the Dispute Avoidance/Adjudication Board (DAAB). A standing board for the whole project is intended — one that can help the parties avoid disputes, not just resolve those that have already arisen.
The 2017 philosophy: it is cheaper and faster to prevent a dispute than to win it.
More procedure and certainty
The second editions are markedly more detailed:
- Clear time limits and steps for the Engineer’s actions, including the agreement-or-determination mechanism (Sub-Clause 3.7).
- A requirement for the Engineer to act neutrally when making determinations.
- Detailed procedures for notices, programmes, tests and payments.
- Exceptional Events in place of the former Force Majeure (Clause 18).
The price of this certainty is volume and complexity: the contracts require more disciplined administration and careful record-keeping.
What this means in practice
- Process over improvisation. Time limits and formal steps must be followed to the letter.
- Records decide. Contemporaneous records become even more valuable.
- The Engineer’s role grew procedurally — and requires neutrality.
If your project uses the 1999 editions and the team is used to them, moving to 2017 will require re-tuning your administration processes. The differences can be worked through for a specific contract in a consultation.
Bridge Consult
Prepared by the experts at Bridge Consult — a practising team in FIDIC contracts, claims and MDB projects. Need help with a real contract?
Request a consultation