Knowledge
Practice ·June 11, 2026 ·6 min

Variations under Clause 13: how to instruct and value them

A Variation is the lawful tool for changing the works under FIDIC. Who can initiate it, how to instruct it, how to value it, and where the line with a claim lies.

Author Larisa Belousova — Founder and Director, BRIDGE Consult LLC FCCE · FCCP · MCIArb
VariationsClause 13ValuationChanges

Practical article map

Contract lens Practice
Key points
Clause 13
How to use this article
01 Issue 02 Evidence 03 Action

Start with the contract issue, test the evidence, then define the practical next step.


No major project runs exactly to the original design. Quantities change, new requirements appear, site conditions surface. FIDIC provides a lawful mechanism for this — the Variation under Clause 13.

What a Variation is

A Variation is a change to the Works made under Clause 13: adding, omitting or changing the quantity, quality, sequence or character of the work. This is not a claim or a dispute — it is the normal tool for managing the contract.

Who initiates it

The right to initiate a change belongs to the Employer’s side — usually through an Engineer’s instruction (in the Silver Book, the Employer’s Representative). The Contractor may propose a change (value engineering), but the Employer’s side puts it into effect.

The Contractor must carry out reasonable Variations — but within the contract and with the right to an adjustment of price and time.

The procedure (Sub-Clause 13.3)

  1. Initiation. The Engineer either instructs a Variation or asks the Contractor for a proposal.
  2. Contractor’s proposal. The impact on design, programme and price; justification.
  3. Agreement or determination. Through the Sub-Clause 3.7 mechanism — the valuation of cost and time.

How it is valued

Valuation generally follows this order of priority:

  • at the contract rates (BoQ/Schedule), if the work is similar;
  • at adjusted rates, if the character or quantity differs significantly;
  • at a reasonable cost (new rates), if there are no comparables.

This also covers adjustments for changes in legislation and cost (Sub-Clause 13.6/13.7 depending on the edition).

Where the line between a Variation and a claim lies

This is a frequent source of disputes:

  • Variation — the employer/Engineer instructed the change. Handled under Clause 13.
  • Claim — a party has acquired a right (to payment/time) because of an event or breach. Handled under Clause 20 with a 28-day notice.

Sometimes one event gives rise to both. If work is done “on instruction” but not formally treated as a Variation, record it and, if necessary, submit a claim so you don’t lose the right to payment.

Practical tips

  • Do not perform significant extra works without a written instruction — verbal directions are hard to prove.
  • Calculate the impact on the programme, not just on cost.
  • If the instruction exceeds the Engineer’s authority, note it.
  • Keep contemporaneous records — they decide the outcome of the valuation.

For more on claims, see “The 28-day rule”. Need a specific change valued? Contact our experts.

Bridge Consult

Prepared by the experts at Bridge Consult — a practising team in FIDIC contracts, claims and MDB projects. Need help with a real contract?

Request a consultation