FIDIC Claims Playbook

Pudratchi uchun qisqa playbook: hodisadan keyingi birinchi kunlarda nima qilish, notice ni qanday himoya qilish, qaysi records yig‘ish va claim file tuzish.

Ishchi struktura

01

Event control

Hodisa, awareness date, affected activities, source party va time/cost impact ni yozib qo‘ying.

02

Notice discipline

28-day notice, recipient, channel, authorised representative va Particular Conditions talablarini tekshiring.

03

Evidence register

Daily records, photos, site instructions, RFIs, minutes, correspondence, programme updates va cost records yig‘ing.

04

EOT path

Hodisani critical path, baseline, updates, mitigation va concurrency analysis bilan bog‘lang.

05

Quantum path

Prolongation, disruption, direct cost, overheads, plant/labour, substantiation va audit trail ni ajrating.

06

DAAB readiness

Chronology, entitlement map, notices, evidence bundle va decision log ni bitta claim file da saqlang.

Hodisadan keyingi 14 kunlik sprint

Claim control sprint

  1. Day 0–1: event file ochish va internal alert berish.
  2. Day 1–3: notice draft va service requirements tekshiruvi.
  3. Day 3–7: baseline/update programme va affected activities ni belgilash.
  4. Day 7–10: site records, photos, instructions va cost signals yig‘ish.
  5. Day 10–14: entitlement note, evidence gaps va next action owner tayyorlash.

Claim file spine

Notice registerChronologyEntitlement mapProgramme evidenceQuantum workbookDAAB bundle

Bu FIDIC.uz amaliy materiali, legal advice emas. Real dispute uchun contract wording, Particular Conditions va loyiha faktlari kerak.