DAAB Site Visits: preparing the file, issue list and project narrative
A practical checklist for DAAB site visits: chronology, issue map, records, photos, programme snapshots and dispute avoidance boundaries.
A poor DAAB visit starts in a familiar way: the Board arrives, the parties show concrete, pipes and charts, and within two hours everyone is arguing about a claim that nobody has properly mapped by date.
A good site visit works differently. The Board receives a clear project narrative, understands the key issues, sees the records that exist, and can help the parties avoid turning every problem into a formal referral.
Site visit vs formal referral
The article on the DAAB under FIDIC 2017 explains the dispute ladder: Engineer’s determination, DAAB, Notice of Dissatisfaction, amicable settlement and arbitration.
A site visit is earlier and broader. Its value is not only that the Board sees the site. Its value is that an independent board gradually understands sequence, constraints and recurring issues.
Do not mix:
- dispute avoidance - early discussion, risk identification and informal assistance where allowed;
- formal referral - the procedural submission of a specific dispute for decision.
If the parties confuse these modes, they either overload the visit with legal submissions or arrive with no useful material.
What to prepare before the visit
The DAAB does not need a 20 GB archive. It needs managed context.
1. Project snapshot
A short 2-4 page orientation note:
- parties and contract form;
- current contract price and Time for Completion;
- commencement date and completion dates;
- current progress status;
- major milestones;
- key packages or subcontractors;
- critical constraints;
- current high-risk issues.
This is not advocacy. It is orientation.
2. Chronology
For each major issue, prepare:
- date;
- event;
- instruction, notice or correspondence reference;
- affected work area or activity;
- current status.
Chronology should be boring and verifiable. If it sounds like a speech for one side, the Board will trust it less.
3. Issue list
The issue list is the core document.
| Issue | Why it matters | Current status | What the Board should understand |
|---|---|---|---|
| delayed access | affects sequence or critical path | notices issued, mitigation ongoing | access links to specific activities |
| design approval delays | blocks procurement or works | submissions under review | workflow discipline is needed |
| variation valuation | payment and cash-flow exposure | rates disputed | measurement trail matters |
| ESHS incident | affects method or reporting | corrective action open | keep it separate from unrelated delay |
Not every issue should become a dispute. Every material issue should be understandable.
4. Visual file
Photos help only when they have context:
- date and location;
- before/after where relevant;
- activity ID or work package;
- short caption;
- no unnecessary repetition.
Twenty-five precise photos are better than 400 images without context.
5. Programme snapshots
If time is involved, the Board needs more than percentage progress:
- baseline reference;
- last accepted or reviewed programme;
- current update;
- affected activities;
- critical or near-critical path explanation;
- mitigation or recovery measures.
For delay evidence, see EOT and delay analysis.
How to conduct the visit
A DAAB visit is not a stage for one side’s victory presentation. A practical format is:
- Joint opening meeting.
- Neutral project update.
- Site walk focused on agreed areas.
- Issue-by-issue discussion.
- Clarification of records needed.
- Summary of action points.
- Minutes or agreed note, where appropriate.
The parties should agree in advance what can be discussed informally and what is too close to a formal dispute.
What not to do
Do not turn the visit into an arbitration hearing. If a dispute has been formally referred, follow the procedure. If this is an avoidance visit, do not arrive with 150 pages of legal submissions unless that mode is agreed.
Do not hide weak points. The Board usually senses selective chronology. Separate agreed facts, disputed facts and missing records.
Do not fight every sentence on site. The visit is for understanding. Constant cross-examination destroys that value.
Do not ignore confidentiality and privilege. Sensitive packs should be reviewed before circulation.
Minimum DAAB visit pack
| Section | Size | Purpose |
|---|---|---|
| Project snapshot | 2-4 pages | Orient the Board |
| Issue list | 1 table | Show active risk areas |
| Chronology | per major issue | Separate dates from arguments |
| Correspondence index | references, not archive | Provide checkability |
| Programme snapshots | 3-5 extracts | Show time impact |
| Photo pack | 15-30 photos | Anchor site reality |
| Action tracker | 1 table | Close practical next steps |
FAQ
Is a legal submission needed for every DAAB visit?
Usually not for routine or avoidance visits. Sensitive issues should still be reviewed with legal support.
Who should prepare the visit pack?
Normally the Contract Manager, planner, QS, site team and legal support. A lawyer-only pack may be weak on facts; a site-only pack may be weak on contract logic.
Can claims be discussed during a site visit?
Yes, if consistent with the contract, DAAB rules and agreed purpose. The parties must know whether this is early discussion, informal assistance or formal dispute process.
Bridge Consult helps prepare DAAB visit packs, issue lists, chronologies and dispute avoidance workflows for FIDIC projects.
Sources and further reading
- FIDIC, Conditions of Contract for Construction, 2017 edition.
- FIDIC, Dispute Avoidance/Adjudication Agreement and procedural materials accompanying the 2017 suite.
- Dispute Resolution Board Foundation, Dispute Board Manual and practice materials.
- See also: DAAB explained, Claims substantiation and EOT and delay analysis.
Bridge Consult
Prepared by the experts at Bridge Consult — a practising team in FIDIC contracts, claims and MDB projects. Need help with a real contract?
Request a consultation