FIDIC EOT claim: muddatni uzaytirish va delay damagesdan himoya
EOT claim bo‘yicha sahifa: Sub-Clause 8.5, 20.2, 28 kunlik notice, delay analysis, programme evidence va delay damages.
Maqolaning amaliy xaritasi
Avval shartnomaviy muammoni aniqlang, keyin dalillarni tekshiring va amaliy keyingi qadamni belgilang.
EOT claim — “muddatni uzaytirib bering” degan xat emas. Bu dalillar tizimi: hodisa, shartnomaviy huquq, o‘z vaqtida notice, critical path ta’siri va hisoblangan davr.
Huquqiy mantiq
Sub-Clause 8.5 Extension of Time huquqini beradi, Sub-Clause 20.2 esa procedure belgilaydi. Birinchi xavf — 28 kunlik notice. U o‘tkazib yuborilsa, faktlar kuchli bo‘lsa ham EOT huquqi yo‘qolishi mumkin.
Texnik mantiq
EOT programme orqali isbotlanadi: baseline, updates, faktik sanalar, windows/time-slice yoki boshqa delay-analysis method. Employer delay contractor concurrent delaydan ajratilishi kerak.
Keyingi qadam
Muddatni Time-bar kalkulyatorda tekshiring, ta’sirni EOT Delayda baholang va dalillarni Claim Readinessda sinang. Asosiy maqola: EOT va delay analysis.
FAQ
Mavzu bo‘yicha savollar
EOT claim nima?
Bu shartnoma bo‘yicha Extension of Time huquqini beradigan hodisa sabab Time for Completionni uzaytirish talabi.
EOT avtomatik tarzda delay damagesni olib tashlaydimi?
Yo‘q. EOT faqat critical path ta’siri isbotlangan davr uchun va notice procedure bajarilgan bo‘lsa himoya qiladi.
EOT uchun qanday dalillar kerak?
Notice, baseline va updated programme, contemporary records, causation, critical path analysis va kunlar hisobi.
Bridge Consult
Material Bridge Consult ekspertlari — FIDIC shartnomalari, claims va XTB loyihalari bo‘yicha amaliyotchi jamoa tomonidan tayyorlangan. Real shartnoma bo‘yicha yordam kerakmi?